I. Discussion of PIFs for assignment
P080401.1 SGP/SIRS/C1 - Wiring problem in Upwelling LW measurement
Discussion:
Actions: OK
Assign To: Gotseff, ask Jimmy to follow up
CC: Long, MacFarlane, Rusk, Breedlove, Orr, Voyles, Stoffel,
Hartsock, DQO
P080404.1 NSA/SGP/TWP/SONDE - Occasional incorrect surface values of T/RH
Discussion: RID-493
Actions: OK
Assign To: Keck
CC: Holdridge, Ritsche, Rusk, Jones, Nitschke, Ivey, Zirzow, REPO, DQO
II. CARs submitted for PIF closure
III. Attachments
A080214.2.6 Submitted by Richard Eagan for
P080214.2 SGP/EF - Time-synching protocol problems
Discussion:
Actions: OK
IV. DQRs
D070503.2 SGP/SWATS/E10 - Instrument problem
Discussion:
Actions: hold
D070514.5 FKB/AERI/M1 - Unknown
Discussion:
Actions: hold
D071026.2 SGP/SWATS/E12 - Instrument logger problem
Discussion:
Actions: hold
D071218.1 FKB/AOS/M1 - failed neph motor
Discussion:
Actions: hold
D080326.2 NSA/METTWR/C1 - 2m Wind Direction Sensor Freezing
Discussion:
Actions: OK
CC: Ritsche, Verlinde, Bahrmann, Richardson, DQO
D080402.2 FKB/MWRHF/M1 - Questionable calibration
Discussion:
Actions: hold, ask Maria to quantify what is meant by large.
D080403.2 SGP/WACR/C1 -
Discussion:
Actions: OK, add subject: Contamination with AMF WACR data
CC: Widener, Johnson, Hartsock, DQO
Review of Open-Ended DQRs:
Review of Warehouse DQRs:
Review of DQRs on Hold:
V. Overviews of Problems
Instruments - Jimmy Voyles
MFRSR issues continuing, Gary is doing some processing,
system changes etc., generally overcommitted.
Talking about maybe improving the calibration procedure to
ease the load on the mentor. Maybe with OSS tracking the
calibration.
OSS development on schedule now. Site common shipping tool
and calibration will be tackled next. Jimmy will send OSS
meeting minutes to Rick.
WACR Radar for China is back at SGP, trying to get ready to
ship to China soon.
MMCR PIRAQ upgrade.
ARM Operations - Doug Sisterson
Engineering - Jim Mather
Archive - Raymond McCord
Found a possible problem with site_transfer between iop
system and storage system. Large transfers, e.g. 1.5GB
iop-data-tar-bundles, only transfer partially.
Will write a BCR on interface changes on IOP server, to
coordinate any dependencies across the ARM Web-world and fix
potential broken URLs for the new login-procedure.
Data Quality Office - Randy Peppler
take Nathan Hiers off the DQO mailing list, he is graduating
and has already taken another job.
Problem/Data Quality Reporting - Robin Perez
External Data Center - Rick Wagener
VI. Review of Special Data Holdings
Next week: Randy is out.
will hold call, only if necessary.