The agenda for this meeting is available here.

Problem Review Board Members present (x=absent/excused):
x-Jim Mather                    x-Doug Sisterson
  Raymond McCord                  Jimmy Voyles
  Randy Peppler                   Richard Wagener
x-Robin Perez
I. Discussion of PIFs for assignment
P080401.1	 SGP/SIRS/C1 - Wiring problem in Upwelling LW measurement
Discussion: Actions: OK Assign To: Gotseff, ask Jimmy to follow up CC: Long, MacFarlane, Rusk, Breedlove, Orr, Voyles, Stoffel, Hartsock, DQO P080404.1 NSA/SGP/TWP/SONDE - Occasional incorrect surface values of T/RH
Discussion: RID-493 Actions: OK Assign To: Keck CC: Holdridge, Ritsche, Rusk, Jones, Nitschke, Ivey, Zirzow, REPO, DQO
II. CARs submitted for PIF closure
III. Attachments
A080214.2.6    Submitted by Richard Eagan for
    P080214.2	 SGP/EF - Time-synching protocol problems
      Discussion:
      Actions: OK

IV. DQRs
D070503.2           SGP/SWATS/E10 - Instrument problem
      Discussion:
      Actions: hold

D070514.5           FKB/AERI/M1 - Unknown
      Discussion:
      Actions: hold

D071026.2           SGP/SWATS/E12 - Instrument logger problem
      Discussion:
      Actions: hold

D071218.1           FKB/AOS/M1 - failed neph motor
      Discussion:
      Actions: hold

D080326.2           NSA/METTWR/C1 - 2m Wind Direction Sensor Freezing
      Discussion:
      Actions: OK
      CC: Ritsche, Verlinde, Bahrmann, Richardson, DQO

D080402.2           FKB/MWRHF/M1 - Questionable calibration
      Discussion:
      Actions: hold, ask Maria to quantify what is meant by large.

D080403.2           SGP/WACR/C1 -
      Discussion:
      Actions: OK, add subject: Contamination with AMF WACR data
      CC: Widener, Johnson, Hartsock, DQO

    Review of Open-Ended DQRs:

    Review of Warehouse DQRs:

    Review of DQRs on Hold:


V. Overviews of Problems
       Instruments - Jimmy Voyles
          MFRSR issues continuing, Gary is doing some processing,
          system changes etc., generally overcommitted.
          Talking about maybe improving the calibration procedure to
          ease the load on the mentor.  Maybe with OSS tracking the
          calibration.  
	  OSS development on schedule now.  Site common shipping tool
          and calibration will be tackled next.  Jimmy will send OSS
          meeting minutes to Rick.
          WACR Radar for China is back at SGP, trying to get ready to
          ship to China soon.
	  MMCR PIRAQ upgrade.
       ARM Operations - Doug Sisterson
       Engineering - Jim Mather
       Archive - Raymond McCord
          Found a possible problem with site_transfer between iop
          system and storage system.  Large transfers, e.g. 1.5GB
          iop-data-tar-bundles, only transfer partially.
	  Will write a BCR on interface changes on IOP server, to
          coordinate any dependencies across the ARM Web-world and fix
          potential broken URLs for the new login-procedure. 
       Data Quality Office - Randy Peppler
          take Nathan Hiers off the DQO mailing list, he is graduating
          and has already taken another job.
       Problem/Data Quality Reporting - Robin Perez
       External Data Center - Rick Wagener

VI. Review of Special Data Holdings

Next week: Randy is out.
will hold call, only if necessary.